This page contains annotated photos from the construction of a Mid-Tex Home.
Lot. The Reserve at Lakeland Meadows. Clients wrap-up plans with Jason Thomas. |  |
Week 1 Foundation is poured. Clients choose a door, transom window and sidelights. |  |
Foundation dries.
|  |
Week 2 Framing begins.
|  |
Week 3 Framing - Day Three
|  |
Framing - Day Four
|  |
Framing - Day Five, OSB installation
|  |
Week 4 House wrap installed. Clients lock 120-day interest rate. |  |
House wrap on back porch.
|  |
Week 7 Major framing complete. Preliminary selections made: tile, paint colors, master shower/hall shower plumbing fixtures, roof color, brick choice. |  |
Week 8 Windows installed
|  |
Bricking begins.
|  |
Sheetrock installed.
|  |
Back of house complete.
|  |
Bricking the front of the house.
|  |
Week 9 Nearly completed bricked front.
|  |
Bricking complete.
|  |
Bricked entry with keystone.
|  |
Installation of cabinets begins.
|  |
Week 10 Built-in desk installed in front bedroom. Final Stain Decided for all cabinets. Change orders received for the following: Kitchen Countertop upgrade, added built-in TV entertainment center, added Austin Stone accents to brickwork. |  |
Week 11 Kitchen cabinets, fully installed. Various plumbing fixtures purchased. |  |
Built-in entertainment center. Appliances for kitchen chosen. |  |
Front bedroom cabinets stained.
|  |
Hall bath cabinets stained.
|  |
Window casing and fluted trim added.
|  |
Fireplace trim added.
|  |
Dining room window casing added.
|  |
Week 12 Fluted trim around French Doors.
|  |
Maple cabinets stained.
|  |
Walls and trim painted. Tile selections finalized. Cultured marble finalized. |  |
Week 13 Lighting fixtures installed in kitchen. Bath hardware finalized. |  |
Lighting fixtures installed in master bath.
|  |
Fans on porch installed.
|  |
Mailbox constructed.
|  |
Cultured marble surround installed. Tile installed. Cabinet pulls finalized. |  |
Week 14 Cultured marble shower and tub installed. Tile installed. Backsplash for kitchen and utility room chosen. |  |
Tile installed in kitchen.
|  |
Tile installed in dining.
|  |
Week 16 Front door installed. Master shower glass and hardware chosen. |  |
Plumbing fixtures installed.
|  |
Kitchen backsplash installed.
|  |
Week 18 Master Shower glass installed. Clients send final information to mortgage company |  |
Week 19 House passes final inspection. Power company transfers service to customer. Living Room: Lighting fixtures tested. |  |
Kitchen with island light.
|  |
Exterior lights, front.
|  |